You need to make sure that no task in this project plan has a question mark in its Duration field

You are entering tasks in a project plan in Microsoft Office Project Standard 2007. Each task has an estimated duration. You need to make sure that no task in this project plan has a question mark in its Duration field. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Disable the option to show that tasks have estimated durations.

B.
Change the width of the Duration column so the question mark is not visible.

C.
Create a new project plan based on a template that does not have estimated durations.

D.
Re-enter the same durations so the question marks representing the estimates disappear.