PrepAway - Latest Free Exam Questions & Answers

You need to compare the Gantt chart before and after the update within the same project plan

You are preparing to update the status of a baselined project plan in Microsoft Office Project Standard 2007. You need to compare the Gantt chart before and after the update within the same project plan. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Capture a picture of the project plan.

B.
Save the project plan as a Microsoft Office Excel workbook.

C.
Generate a visual report of the project plan before and after the update.

D.
Save another baseline, and then display it in the Gantt chart with the current plan.


Leave a Reply