PrepAway - Latest Free Exam Questions & Answers

You need to have Project automatically reschedule Task A if Task B finishes earlier or later than scheduled

You are managing two projects in Microsoft Office Project Standard 2007. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if Task B finishes earlier or later than scheduled. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Display the Task Drivers pane to manage the automatic rescheduling.

B.
Display the external predecessors and successors in both project plans.

C.
Create a master project that includes both project plans, and then create a cross-project link.

D.
Create a master project that includes both project plans, and then assign the same calendar to both tasks.


Leave a Reply