You need to reschedule the tasks for completion at a later date

While reviewing a project schedule in Microsoft Office Project Standard 2007, you find a number of tasks that are overdue and have not been completed. You need to reschedule the tasks for completion at a later date. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Set the progress lines at the current date.

B.
In the Project Information dialog box, update the status date.

C.
Update the tasks remaining durations to extend beyond the current date.

D.
In the Update Project dialog box, move the incomplete tasks past the current date.