You need to ensure that the ACWP shows data other than $0

You measure the performance of a project you are tracking in Microsoft Office Project Standard 2007 by updating the completion percentage of the tasks. The actual cost of work performed (ACWP) for all tasks is $0.00. The project has a baseline and all values have been calculated. You need to ensure that the ACWP shows data other than $0.00. What should you do first?

PrepAway - Latest Free Exam Questions & Answers

A.
Assign budget resources to the project summary task.

B.
Enter standard resource rates that are greater than zero.

C.
Select the Manual calculation mode, and then perform a calculation.

D.
Select the Physical % Complete option for earned value purposes.