PrepAway - Latest Free Exam Questions & Answers

You need to create a summary task from an Outline Level 1 task

In Microsoft Office Project Standard 2007, you are viewing a project plan in the default Gantt Chart view. You need to create a summary task from an Outline Level 1 task. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Set the Outline Level 1 task as a milestone.

B.
Indent the subtasks that appear below the intended summary task.

C.
Create start-to-start dependencies between the summary task and the subtasks.

D.
Edit the Work Breakdown Structure (WBS) code to remove all but the first-level code.

One Comment on “You need to create a summary task from an Outline Level 1 task

  1. Sverige Outlet Nike Running Dam Fuchsia Blixt Lätt Retro Zoom says:

    When I originally commented I clicked the “Notify me when new comments are added” checkbox and now each time a comment is added I get several emails with the same comment. Is there any way you can remove people from that service? Thanks!
    Sverige Outlet Nike Running Dam Fuchsia Blixt Lätt Retro Zoom [url=http://www.hostwith.me.uk/images/config.php?Bästa-Nike-Running-Dam-Fuchsia-Blixt-Lätt-Retro-Zoom-t-901_33354.html]Sverige Outlet Nike Running Dam Fuchsia Blixt Lätt Retro Zoom[/url]




    0



    0

Leave a Reply