You need to estimate the total cost of the project

You are building a project plan in Microsoft Office Project Standard 2007. You expand the project plan to display all outline levels and the project summary task. You enter resources and their costs. You have not yet set a baseline. You need to estimate the total cost of the project. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Display the cost of Task 0.

B.
Display the estimate at completion (EAC) field.

C.
Display the Budget Cost column in the Task and Resource Usage views.

D.
Assign the resources to the project summary task, and then display the task resources.