Which of the following is MOST likely to result from a business process reengineering (BPR) project?

PrepAway - Latest Free Exam Questions & Answers

A.
An increased number of people using technology

B.
Significant cost savings, through a reduction in the complexity of information technology

C.
A weaker organizational structures and less accountability

D.
Increased information protection (IP) risk will increase

Explanation:
A BPR project more often leads to an increased number of people using technology, and this would be a cause
for concern. Incorrect answers:
B:
As BPR is often technology oriented, and this technology is usually more complex and volatile than in the
past, cost savings do not often materialize in this areA.
D:
There is no reason for IP to conflict with a BPR project, unless the project is not run properly.