A.
Warm site

B.
Mobile site

C.
Hot site

D.
Cold site

Explanation:
Generally a cold site is contracted for a longer period at a lower cost. Since it requires more time to make a
cold site operational, it is generally used for noncritical applications. A warm site is generally available at a
medium cost, requires less time to become operational and is suitable for sensitive operations. A mobile site is
a vehicle ready with all necessary computer equipment that can be moved to any cold or warm site depending
upon the need. The need for a mobile site depends uponthe scale of operations. A hot site is contracted for a
shorter time period at a higher cost and is better suited for recovery of vital and critical applications.