Which of the following should an IS auditor review to g…

Which of the following should an IS auditor review to gain an understanding of the effectiveness of controls
over the management of multiple projects?

PrepAway - Latest Free Exam Questions & Answers

A.
Project database

B.
Policy documents

C.
Project portfolio database

D.
Program organization

Explanation:
A project portfolio database is the basis for project portfolio management. It includes project data, such as
owner, schedules, objectives, project type, status and cost. Project portfolio management requires specific
project portfolio reports. A project database may contain the above for one specific project and updates to
various parameters pertaining to the current status of that single project. Policy documents on project
management set direction for the design, development, implementation and monitoring of the project. Program
organization is the team required (steering committee, quality assurance, systems personnel, analyst,
programmer, hardware support, etc.) to meet the delivery objective of the project.