PrepAway - Latest Free Exam Questions & Answers

An offsite information processing facility having elect…

An offsite information processing facility having electrical wiring, air conditioning and flooring, but no computer
or communications equipment is a:

PrepAway - Latest Free Exam Questions & Answers

A.
cold site.

B.
warm site.

C.
dial-up site.

D.
duplicate processing facility.

Explanation:
A cold site is ready to receive equipment but does not offer any components at the site in advance of the need.
Incorrect answers:
B:
A warm site is an offsite backup facility that is configured partially with network connections and selected
peripheral equipment, such as disk and tape units, controllers and CPUs, to operate an information processing
facility.
D:
A duplicate information processing facility is a dedicated, self-developed recovery site that can back up
critical applications.