Which of the following is an appropriate test method to apply to a business continuity plan (BCP)?

PrepAway - Latest Free Exam Questions & Answers

A.
Pilot

B.
Paper

C.
Unit

D.
System

Explanation:
A paper test is appropriate for testing a BCP. it is a walkthrough of the entire plan, or part of the plan, involving
major players in the plan’s execution, who reason out what may happen in a particular disaster. Choices A, C
and D are not appropriate for a BCP.