To minimize the cost of a software project, quality man…

To minimize the cost of a software project, quality management techniques should be applied:

PrepAway - Latest Free Exam Questions & Answers

A.
as close to their writing (i.e., point of origination) as possible.

B.
primarily at project start-up to ensure that the project is established in accordance with organizational
governance standards.

C.
continuously throughout the project with an emphasis on finding and fixing defects primarily during testing to
maximize the defect detection rate.

D.
mainly at project close-down to capture lessons learned that can be applied to future projects.

Explanation:
While it is important to properly establish a software development project, quality management should be
effectively practiced throughout the project. The major source of unexpected costs on most software projects is
rework. The general rule is thatthe earlier in the development life cycle that a defect occurs, and the longer it
takes to find and fix that defect, the more effort will be needed to correct it. A well-written quality management
plan is a good start, but it must also be actively applied. Simply relying on testing to identify defects is a
relatively costly and less effective way of achieving software quality. For example, an error in requirements
discovered in the testing phase can result in scrapping significant amounts of work. Capturing lessons learned
will be too late for the current project. Additionally, applying quality management techniques throughout a
project is likely to yield its own insights into the causes of quality problems and assist in staff development.