Which of the following techniques would BEST help an IS…

Which of the following techniques would BEST help an IS auditor gain reasonable assurance that a project can
meet its target date?

PrepAway - Latest Free Exam Questions & Answers

A.
Estimation of the actual end date based on the completion percentages and estimated time to complete,
taken from status reports

B.
Confirmation of the target date based on interviews with experienced managers and staff involved in the
completion of the project deliverables

C.
Extrapolation of the overall end date based on completed work packages and current resources

D.
Calculation of the expected end date based on current resources and remaining available project budget

Explanation:
Direct observation of results is better than estimations and qualitative information gained from interviews or
status reports. Project managers and involved staff tend to underestimate the time needed for completion and
the necessary time buffers for dependencies between tasks, while overestimating the completion percentage
for tasks underway (80:20 rule). The calculation based on remaining budget does not take into account the
speed at which the project has been progressing.