The reason for establishing a stop or freezing point on the design of a new system is to:

PrepAway - Latest Free Exam Questions & Answers

A.
prevent further changes to a project in process.

B.
indicate the point at which the design is to be completed.

C.
require that changes after that point be evaluated for cost-effectiveness.

D.
provide the project management team with more control over the project design.

Explanation:
Projects often have a tendency to expand, especially during the requirements definition phase. This expansion
often grows to a point where the originally anticipated cost-benefits are diminished because the cost of the
project has increased. When this occurs, it is recommended that the project be stopped or frozen to allow a
review of all of the cost-benefits and the payback period.