PrepAway - Latest Free Exam Questions & Answers

The use of a GANTT chart can:

The use of a GANTT chart can:

PrepAway - Latest Free Exam Questions & Answers

A.
aid in scheduling project tasks.

B.
determine project checkpoints.

C.
ensure documentation standards.

D.
direct the post-implementation review.

Explanation:
A GANTT chart is used in project control. It may aid in the identification of needed checkpoints but its primary
use is in scheduling. It will not ensure the completion of documentation nor will it provide direction for the postimplementation review.


Leave a Reply