An IS auditor finds that a system under development has 12 linked modules and each item of data can carry up
to 10 definable attribute fields. The system handles several million transactions a year. Which of these
techniques could an IS auditor use to estimate the size of the development effort?

PrepAway - Latest Free Exam Questions & Answers

A.
Program evaluation review technique (PERT)

B.
Counting source lines of code (SLOC)

C.
Function point analysis

D.
White box testing

Explanation:
Function point analysis is an indirect method of measuring the size of an application by considering the number
and complexity of its inputs, outputs and files. It is useful for evaluating complex applications. PERT is a project
management technique that helps with both planning and control. SLOC gives a direct measure of program
size, but does not allow for the complexity that may be caused by having multiple, linked modules and a variety
of inputs and outputs. White box testing involves a detailed review of the behavior of program code, and is a
quality assurance technique suited to simpler applications during the design and build stage of development.