PrepAway - Latest Free Exam Questions & Answers

Integrating business continuity planning (BCP) into an …

Integrating business continuity planning (BCP) into an IT project aids in:

PrepAway - Latest Free Exam Questions & Answers

A.
the retrofitting of the business continuity requirements.

B.
the development of a more comprehensive set of requirements.

C.
the development of a transaction flowchart.

D.
ensuring the application meets the user’s needs.

Explanation:
Integrating business continuity planning (BCP) into the development process ensures complete coverage of the
requirements through each phase of the project. Retrofitting of the business continuity plan’s requirements
occurs when BCP is not integrating into the development methodology. Transaction flowcharts aid in analyzing
an application’s controls. A business continuity plan will not directly address the detailed processing needs of
the users.


Leave a Reply