PrepAway - Latest Free Exam Questions & Answers

Depending on the complexity of an organization’s business…

Depending on the complexity of an organization’s business continuity plan (BCP), the plan may be developed
as a set of more than one plan to address various aspects of business continuity and disaster recovery, in such
an environment, it is essential that:

PrepAway - Latest Free Exam Questions & Answers

A.
each plan is consistent with one another.

B.
all plans are integrated into a single plan.

C.
each plan is dependent on one another.

D.
the sequence for implementation of all plans is defined.

Explanation:
Depending on the complexity of an organization, there could be more than one plan to address various aspects
of business continuity and disaster recovery. These do not necessarily have to be integrated into one single
plan. However, each plan has tobe consistent with other plans to have a viable business continuity planning
strategy. It may not be possible to define a sequence in which plans have to be implemented, as it may be
dependent on the nature of disaster, criticality, recovery time, etc.


Leave a Reply