Which of the following would MOST likely contain warranty information for the project deliverable?

Which of the following would MOST likely contain warranty information for the project deliverable?

PrepAway - Latest Free Exam Questions & Answers

A.
Scope statement

B.
Cost baseline

C.
Risk assessment

D.
Transition plan

Explanation: