A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of
the following should the project manager do FIRST to complete the project on time?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Lower the quality standards for the finished product.
B.
Analyze the impact of the change.
C.
Eliminate 10 percent of the projects resources.
D.
Document the approved change request.
Explanation: