PrepAway - Latest Free Exam Questions & Answers

Which of the following actions should the project manager undertake FIRST?

The change control board has requested that a project manager evaluate the impact of a major
change request that will affect the timetable of several work-packages. Which of the following
actions should the project manager undertake FIRST?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a modified version of the project schedule applying the critical path method.

B.
Call a project team meeting to use combined expert judgment to accept or reject the change
request.

C.
Create a Pareto chart for the outputs from the specific work-packages identified by the change
control board.

D.
Crash the schedule to meet the original deadlines.

Explanation:


Leave a Reply