Which of the following cost estimating techniques was used?

A project manager creates a detailed list of costs for each activity involved in the project and then
uses the sum of the individual activities to create the budget. Which of the following cost
estimating techniques was used?

PrepAway - Latest Free Exam Questions & Answers

A.
Bottom-up

B.
Expert judgment

C.
Parametric

D.
Top-down

Explanation: