Which of the following would be used during activity sequencing?

A project manager has just completed the work breakdown structure (WBS) with the project team.
Which of the following would be used during activity sequencing?

PrepAway - Latest Free Exam Questions & Answers

A.
Precedence diagramming method

B.
Monte Carlo analysis

C.
Resource availability

D.
Resource leveling technique

Explanation: