PrepAway - Latest Free Exam Questions & Answers

which of the following is the NEXT step the project manager should take, once performance information has been

When ensuring the quality of project deliverables, which of the following is the NEXT step the
project manager should take, once performance information has been gathered?

PrepAway - Latest Free Exam Questions & Answers

A.
Create Gantt charts

B.
Generate change requests

C.
Identify variances

D.
Implement change requests

Explanation: