PrepAway - Latest Free Exam Questions & Answers

Which of the following documents needs to be updated?

The project sponsor has just requested a status report be emailed to all project stakeholders every
two weeks. Which of the following documents needs to be updated?

PrepAway - Latest Free Exam Questions & Answers

A.
Communications plan

B.
Quality plan

C.
Stakeholder analysis report

D.
Work Breakdown Structure (WBS)

Explanation: