PrepAway - Latest Free Exam Questions & Answers

Which of the following sequences represents the correct order for implementing a change request?

Which of the following sequences represents the correct order for implementing a change
request?

PrepAway - Latest Free Exam Questions & Answers

A.
Change is requested, change impact analyzed, change request submitted to board, change
request approved, change implemented.

B.
Change is requested, change implemented, change impact analyzed, change request
submitted to board, change request approved.

C.
Change is requested, change request submitted to board, change impact analyzed, change
request approved, change implemented.

D.
Change is requested, change request submitted to board, change request approved, change
implemented, change impact analyzed.

Explanation:


Leave a Reply