Which of the following is a tool that can be used to identify project team members that are responsible for a

Which of the following is a tool that can be used to identify project team members that are
responsible for a task or deliverable?

PrepAway - Latest Free Exam Questions & Answers

A.
Project charter

B.
Work Breakdown Structure (WBS)

C.
Project schedule

D.
RACI chart

Explanation: