PrepAway - Latest Free Exam Questions & Answers

which of the following is the NEXT step that a project manager should complete?

After identifying the activities in a work package, which of the following is the NEXT step that a
project manager should complete?

PrepAway - Latest Free Exam Questions & Answers

A.
Estimate costs

B.
Identify activities

C.
Build a project schedule

D.
Assign key stakeholders

Explanation:


Leave a Reply