PrepAway - Latest Free Exam Questions & Answers

Which of the following would be the BEST tool to estimate the final duration?

A project team is estimating the amount of time needed to perform an activity. They have
recommended an optimistic, pessimistic, and most likely duration to complete the activity. Which
of the following would be the BEST tool to estimate the final duration?

PrepAway - Latest Free Exam Questions & Answers

A.
PERT

B.
GANTT

C.
GERT

D.
WBS

Explanation:


Leave a Reply