Which of the following is the correct progression of the project life cycle?

Which of the following is the correct progression of the project life cycle?

PrepAway - Latest Free Exam Questions & Answers

A.
Planning, initiating, executing, monitoring / controlling, closing

B.
Initiating, planning, executing, monitoring / controlling, closing

C.
Planning, initiating, monitoring / controlling, executing, closing

D.
Initiating, planning, monitoring / controlling, executing, closing

Explanation: