A project manager needs to identify uncertain events during the planning phase. Which of the
following documents would be the BEST source of this information?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Quality log
B.
Risk register
C.
Issues log
D.
Responsibility assignment matrix
Explanation: