Which of the following risk responses is described in this situation?

Several key resources will be unavailable at the end of the project. The key stakeholders want to
outsource the project to a third party. Which of the following risk responses is described in this
situation?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk avoidance

B.
Risk mitigation

C.
Risk acceptance

D.
Risk transference

Explanation: