Which of the following is a method of transferring the risk?

A project has been delayed due to an ongoing labor dispute. The project sponsor asks the project
manager to transfer the risk to complete the project on time. Which of the following is a method of
transferring the risk?

PrepAway - Latest Free Exam Questions & Answers

A.
Delay the project

B.
Change the project schedule

C.
Outsource the project

D.
Hire more resources

Explanation: