PrepAway - Latest Free Exam Questions & Answers

Which of the following BEST describes this situation?

A project manager has been informed that a project deliverable must be completed by September
1st. Which of the following BEST describes this situation?

PrepAway - Latest Free Exam Questions & Answers

A.
Project assumption

B.
Project constraint

C.
Project risk

D.
Acceptance criteria

Explanation: