which of the following risk management processes did this occur?

A project manager conducted a risk probability and impact assessment with the project team. In
which of the following risk management processes did this occur?

PrepAway - Latest Free Exam Questions & Answers

A.
Qualitative risk analysis

B.
Quantitative risk analysis

C.
Risk response planning

D.
Risk identification

Explanation: