Which of the following correctly identifies the application of a projects quality management plan?

Which of the following correctly identifies the application of a projects quality management plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Quality assurance and quality control both occur in the monitoring / controlling phase.

B.
Quality control occurs in the execution phase, quality assurance occurs in the monitoring /
controlling phase.

C.
Quality assurance occurs in the execution phase, quality control occurs in the monitoring /
controlling phase.

D.
Quality assurance and quality control both occur in the execution phase.

Explanation: