Crashing a schedule involves which of the following?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Performing a re-baseline of the project schedule
B.
Performing critical path activities simultaneously
C.
Adding resources to critical path activities
D.
Estimating the earned value of the project activities
Explanation: