PrepAway - Latest Free Exam Questions & Answers

Which of the following should the project manager do?

A project manager learns that a team member has falsified work experience, and does not have
the knowledge required to complete the task. Which of the following should the project manager
do?

PrepAway - Latest Free Exam Questions & Answers

A.
Reassign the individual to another role on the project team.

B.
Ignore the situation hoping that everything works out for the best.

C.
Assign other individuals to assist on the task to ensure the task does not get delayed further.

D.
Replace the member and ask the team manager to assign a more qualified person.

Explanation:


Leave a Reply