Which of the following tools is the project manager utilizing?

A project manager is performing activity sequencing with the project team. Each activity is written
in a box with arrows linking the boxes according to their dependencies. Which of the following
tools is the project manager utilizing?

PrepAway - Latest Free Exam Questions & Answers

A.
Arrow Diagramming Method (ADM)

B.
Precedence Diagramming Method (PDM)

C.
Critical Path Method (CPM)

D.
Critical Chain Method (CCM)

Explanation: