Which of the following is the main objective for a work breakdown structure (WBS)?
A.
To develop a proven methodology that will assist the project manager with the delegation of
authority.
B.
To decompose the project down into manageable parts.
C.
To develop the estimating and detailed scheme of the project.
D.
To build on individual development, independent of the team efforts.
Explanation:
