The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to
date. The project is currently 50 percent complete. Which of the following is the earned value
(EV)?

A.
$35,624.00
B.
$59,373.33
C.
$71,248.00
D.
$85,497.60
Explanation: