An ongoing project requires several parts manufactured at an outside vendor. If the vendor has
sufficient quantity and can still ship today, the parts should be received in five days; although in
most cases an order of this size requires ten days. Allowing for an upcoming holiday and some
potential bad weather the shipment could take up to twenty-one days. Using the PERT method,
which of the following is the correct time estimate for a parts delivery?

A.
10 days
B.
11 days
C.
21 days
D.
36 days
Explanation: