The ___________is responsible for getting the alternate site into a working and functioning environment, and the ________is responsible for starting the recovery of the original site.

PrepAway - Latest Free Exam Questions & Answers

A.
Restoration team, salvage team

B.
Salvage team, restoration team

C.
Recovery team, restoration team

D.
Recovery team, salvage team

Explanation:
The restoration team should be responsible for getting the alternate
site into a working and functioning environment, and the salvage team should be
responsible for starting the recovery of the original site.