What is the primary goal of disaster recovery planning (DRP)?

What is the primary goal of disaster recovery planning (DRP)?

PrepAway - Latest Free Exam Questions & Answers

A.
Integrity of data

B.
Preservation of business capital

C.
Restoration of business processes

D.
Safety of personnel

Explanation:
Answer D is correct; Loss of human life is the highest impact of any risk; personnel safety is the primary concern of all 10 domains, including business continuity and disaster recovery planning.

Incorrect Answers and Explanations: A, B, and C: Answers A, B, and C are incorrect. All are valid concerns, but none trump personnel safety.

One Comment on “What is the primary goal of disaster recovery planning (DRP)?

  1. joe says:

    Loss of human life is the highest impact of any risk; personnel safety is the primary concern of all 10 domains, including business continuity and disaster recovery planning.