The proper steps for developing a disaster recovery plan are laid out below;
. Develop the continuity planning policy statement.
. Conduct the business impact analysis (BIA).
. Identify preventive controls.
. Develop recovery strategies.
. Develop the contingency plan.
. Test the plan and conduct training and exercises.
. Maintain the plan.