PrepAway - Latest Free Exam Questions & Answers

Which two tasks should be performed when producing a project plan for a Service Availability and Performance

Which two tasks should be performed when producing a project plan for a Service Availability and

Performance Management solution? (Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
Create a work breakdown structure

B.
Schedule working group meetings for the project

C.
Develop a timeline based on a level of effort for each milestone

D.
Identify the team members that will be working on the solution

E.
Develop a system to identify milestones as the project progresses

Explanation:


Leave a Reply