When a Service Availability and Performance Management project manager is developing a
staffing plan, which important task needs to be performed early on?

PrepAway - Latest Free Exam Questions & Answers

A.
Ensure training has occurred for each of the staff

B.
Develop a milestone to staffing organizational chart

C.
Design a plan for each employee that includes appropriate vacation time

D.
Map the required skills for each implementation requirement in the design

Explanation: