The core event management solution for a customer needs to be upgraded to fix user impacting
software issues. The upgrade will enhance the integration capabilities for several downstream
products, but presents a long testing and quality assurance (QA) period to implement.
What would be the next step before including the upgrade as part of the solution requirements?
A.
Compile a scope and project plan for the upgrade
B.
Work with Change and Release Management to compile a schedule for QA
C.
Hold a meeting with IT Operations Management to pitch the benefits of the upgrade
D.
Inform the project sponsors and project stakeholders of the required readjustments of inputs
and obtain agreement
Explanation: