When a Service Availability and Performance Management project manager is developing a
staffing plan, which important task needs to be performed early on?
A.
Ensure training has occurred for each of the staff
B.
Develop a milestone to staffing organizational chart
C.
Design a plan for each employee that includes appropriate vacation time
D.
Map the required skills for each implementation requirement in the design
Explanation: